Contract 2007-2027
184 Scott Street, Unit 9
St. Catharines, Ontario, L2N 1H1
Tel: 905-937-6905
info@qewstcatharines.com

Contact Us


 
Home
History
Background
Work Progress
Upcoming Work
Traffic Impacts
Why the Vibrations
Noise Wall Info
Open Access Session
Bridge Demo Video
Project Photos
Contact Us

Work In Progress

STAGE 5 (2010) - Henley to Skyway QEW Median Work
  • Median High mast lighting along the QEW
  • Finalize QEW median sewer connections
  • QEW median tall wall
  • QEW median grading and paving
  • Martindale east portion construction
  • Niagara structure rehab and deck replacement
  • Ontario structure rehab and deck replacement
  • QEW median surface paving

(2011) Complete Paving

Work Completed to Date

STAGE 1 (2007)
  • QEW north side and south side outside widening including sewers from Seventh Street to Martindale. This work includes the widening of the Third Street Structure.
  • QEW north side and south side outside temporary widening from Ontario Street to Garden City Skyway.
  • Storm sewers on Dunlop, from Geneva to Fitzgerald.

  • Storm Water Management Pond at Ontario Street.

  • Storm Water Management Pond at Spruce Street.

  • Grading and berm construction at the Martindale Ramp from the QEW Toronto bound.

STAGE 2 (2007 & 2008):

  • QEW median removals from Seventh Street to Martindale

  • QEW median storm sewer from Ontario to Bunting.

  • Lake Street bridge work.

  • High Mast lighting at the Seventh Street and Third Street interchange.

  • Demolition of the Lake Street underpass bridge was successfully completed on the weekend of December 13th, 2008.

Stage 3 - Toronto Bound Widening (2008):

  • QEW north side widening from Lake Street to the Garden City Skyway, including widening the Welland and Geneva bridges.
  • Advance Traffic Management System from Ontario to Bunting (MTO Camera's for traffic monitoring).

  • Noise Barriers on south side of QEW on the east and west side of Fitzgerald and on the east side of Niagara Street, specifically around the Storm Water Management Pond at Fitzgerald.

  • Noise Barriers on the north side of the QEW from Lake Street to Geneva Welland Ave.

  • QEW median tall wall and high mast lighting from Seventh Street to Martindale, this included the median widening of the Third Street Structure.

Stage 3-4  - Niagara Bound Widening (2009):

  • Geneva Bridge at QEW Successfully Demolished: April 24/09 at 22.00 till April 27/09 at 06.00

  • Welland Bridge at QEW Successfully Demolished: May 1/09 to 22.00 till May 4/09 at 06.00

  • Noise Barrier on south side of QEW on the east and west side of Fitzgerald and on the east side of Niagara Street, specifically around the Storm Water Management Pond at Fitzgerald. 

  • QEW north and south side widening from Ontario to Lake Street, including noise barrier walls.

  • Lake Street bridge work and landscaping

  • Construction of the west half of the Martindale bridge

  • QEW outside widening on south side from 406 to Bunting.

  • Construction of the south sides of the Welland and Geneva bridges

  • Continue and complete Noise Barrier #2 on the north side of the QEW from Ontario to Lake.

  • Noise Barrier #3 on the south side of QEW from Ontario to Lake Street.

  • Noise Barrier #5 and 10 on the south side of the QEW from Lake to Welland