Continue
with QEW median storm
sewer from Ontario to Bunting. This work is expected to
continue through the winter months (Jan/Feb/March), weather permitting.
-
Continue with Lake Street
bridge work. This work is expected to continue through the
winter months (Jan/Feb/March), weather permitting.
-
Complete the High Mast
lighting at the Seventh Street and Third Street interchange.
This work is expected to continue through the winter months
(Jan/Feb/March),
weather permitting.
-
Complete the High mast
lighting and overhead signs on 406 median. This work is
expected to continue through the winter months
(Jan/Feb/March), weather
permitting.
-
Continue with Advance Traffic
Management System from Ontario to Bunting. This work is
expected to continue through the winter months
(Jan/Feb/March), weather
permitting.
-
Complete the Noise Barrier on
south side of QEW on the east and west side of Fitzgerald
and on the east side of Niagara Street, specifically around
the Storm Water Management Pond at Fitzgerald.
-
QEW median tall wall and
high mast lighting from Seventh Street to Martindale, this
included the median widening of the Third Street Structure.
-
Lake Street bridge
construction, which includes reducing lanes on Lake Street.
-
Martindale bridge
construction, which includes reducing lanes on Martindale
Rd.
-
QEW outside widening on
north side from Ontario to Bunting.
-
Demolition and new
construction of the north side of the Geneva and Welland
Ave. bridges.
-
QEW outside widening on
the north and south side from Ontario to Lake.
-
Noise Barrier #2 on the north
side of the QEW from Ontario to Lake.
-
Noise Barrier #3 on the south
side of QEW from Ontario to Lake Street.